The teardown sequence
- Design and permits for the new house, including any variance.
- Asbestos survey. Under New York’s Industrial Code Rule 56, the owner must get an asbestos survey by a state-certified inspector before demolition. Buildings whose construction began on or after January 1, 1974 are exempt from the survey, but a building slated for demolition without one is assumed to contain asbestos unless it’s documented as free of it (§ 56-5.1(b) and (c), ICR 56). Asbestos found is removed by a licensed abatement contractor first.
- Utility disconnects. Electric, gas, water and sewer or septic are cut off and capped.
- Demolition permit and demolition. The Town of Hempstead’s posted schedule lists $250 for a single- or two-family demolition (Town of Hempstead).
- New foundation, then framing, roofing, rough-ins, inspections, finishes and a new certificate of occupancy.
What it costs
| Item | Figure | Source |
|---|---|---|
| Demolition, Long Island house | $11,400 – $24,100 | HomeBlue |
| Custom home, per sq ft (national) | $200 – $550 | HomeAdvisor |
| Framing, labor and materials, multi-level house (national) | $10 – $19 per sq ft | Angi |
Framing is a small slice of the new-build total. The rest is foundation, roofing, windows, mechanicals, finishes, fees and site work. See framing cost per square foot for the framing piece alone.
Suffolk’s septic rule for replacement houses
A Suffolk County Department of Health Services presentation lists replacing an existing house as one of the triggers for a residential application to the county, and says nitrogen-reducing I/A systems have been required for new construction since 2021 (SCDHS presentation). Budget for a new sanitary system on an unsewered Suffolk lot. Our cesspool guide has more.
Lead paint rules also apply to work on pre-1978 houses; see lead and asbestos rules.
Flood zones and teardowns
On the South Shore, a new house in a FEMA flood zone must be built to current flood rules from the start, which usually means an elevated first floor. For some owners, that’s the reason to rebuild instead of renovate. See the 50% rule.
Stick-built or modular?
Both start with the same demolition and foundation. Compare them on modular vs stick-built, and see what a framing crew does on new home framing.
Frequently asked questions
When does a teardown make more sense than a renovation?
When the existing house needs so much work that you'd replace most of it anyway: a failing foundation, a layout that can't be fixed, a flood-zone house that would have to be elevated, or a small house on a lot that allows much more. If the renovation would cost a large share of a rebuild, price both.
Can I rebuild on the same foundation?
Sometimes. Reusing a sound foundation can save money and, in some towns, preserve existing nonconforming setbacks. But many towns treat removal of most of the house as new construction that must meet current zoning, and an old foundation may not carry a bigger house. Ask the building department and an engineer before you plan around it.
Do I need a demolition permit?
Yes. Long Island towns issue demolition permits separately or as part of the new-building permit. The Town of Hempstead's posted fee schedule, for example, lists $250 for demolishing a single- or two-family house, with no fee when it's part of a permitted alteration.
How long does a teardown and rebuild take?
Plan on design and permits, demolition, then a full new-home build. Construction of the new house usually runs many months. Modular can shorten the on-site part. Ask builders for a written schedule.
Sources
- HomeBlue: cost to demolish a house in Long Island, NY
- HomeAdvisor: cost to build a house (custom homes per square foot, updated June 2026)
- Angi: cost to frame a house (2026)
- NYS Department of Labor: asbestos survey requirements for building permit applicants (Industrial Code Rule 56)
- Town of Hempstead: building department fees, Code § 86-11 (demolition fee)
- Suffolk County Department of Health Services presentation (posted by the Town of Shelter Island)
- NYS Department of Labor: Industrial Code Rule 56 (§ 56-5.1 survey requirement and exemptions)