Town of Hempstead: how the fee works
Code § 86-11, as amended by Local Law 20-2024 effective April 2, 2024, charges residential work $200 up to $1,000 of estimated construction cost, then $18 for each additional $1,000 or fraction. Work started before a permit is $400 plus $36 per additional $1,000 (Town of Hempstead Local Law 20-2024). An approved permit left unpaid more than 90 days adds $200 for each 90-day extension.
| Estimated cost | Permit fee | If started before a permit |
|---|---|---|
| $50,000 | $1,082 | $2,164 |
| $100,000 | $1,982 | $3,964 |
| $150,000 | $2,882 | $5,764 |
| $200,000 | $3,782 | $7,564 |
| $300,000 | $5,582 | $11,164 |
More on the town's rules, including the Levittown district's height and yard limits: Town of Hempstead building permits.
Town of Oyster Bay: how the fee works
The Department of Planning & Development charges a $100 non-refundable application fee, then $100 for the first $1,000 of valuation and $12 for each additional $1,000 or fraction (Town of Oyster Bay fee schedule).
| Valuation | Application + permit fee |
|---|---|
| $50,000 | $788 |
| $100,000 | $1,388 |
| $150,000 | $1,988 |
| $200,000 | $2,588 |
| $300,000 | $3,788 |
Filing requirements, including the second-story footing affidavit: Town of Oyster Bay building permits.
Town of Huntington: how the fee works
Code § 87-23 sets the estimated construction cost from floor area, then charges a $100 residential minimum plus $7 per $1,000 of that estimate or fraction. Work started without a permit is charged three times the fee (Town of Huntington § 87-23).
| Project | Floor area | Town valuation | Permit fee |
|---|---|---|---|
| Rear shed dormer | 400 sq ft | $20,000 | $240 |
| Second story over a ranch | 1,000 sq ft | $80,000 | $660 |
| One-story rear addition | 300 sq ft | $30,000 | $310 |
Plans, survey and accessory-unit rules: Town of Huntington building permits.
Other offices
The Town of North Hempstead takes a $250 initial fee at filing and calculates the exact fee from its Schedule of Construction Costs before issuing the permit; see North Hempstead permits. We add other towns to this calculator only after checking their formula against the town's own published schedule. Until then, call the office listed on Long Island building permits. For the construction side of the budget, see dormer and addition costs or the project cost estimator.