Incorporated Village of Rockville Centre Building Department
- Address
- 110 Maple Avenue, Rockville Centre, NY 11570
- Phone
- (516) 678-9247
- Website
- rvcny.gov/building-department
- Issues permits for
- All of the Incorporated Village of Rockville Centre. Nearby unincorporated areas such as Oceanside and Baldwin file with the Town of Hempstead.
What to file
The Building Department’s posted residential permit package, whose pages carry revision dates from 2011 to 2021, lists (Village of Rockville Centre):
- A completed, notarized application and the building permit application entry form.
- A $135 application fee; the permit fee itself is calculated after review, and a separate check covers the certificate of occupancy or letter of completion.
- A zoning affidavit and an architect’s or engineer’s certificate of compliance.
- Two surveys to scale, no older than five years.
- Two construction drawings stamped by a New York State architect or engineer, including energy code calculations.
- When the work affects the front yard of an interior lot, the average setback of all structures on the same side of the street.
- A site plan showing construction fencing.
- The contractor’s Nassau County home improvement license and insurance; an underwriter’s application from a Rockville Centre licensed electrician; a plumbing permit or affidavit of no plumbing.
- An affidavit of asbestos when asbestos is removed; see lead and asbestos rules.
Applications are filed directly with the residential inspector during set morning and midday windows.
Exterior Design Review
Two conditions send a project to Exterior Design Review: a total cost greater than $300,000, or an increase of 1,000 square feet or more. If your second story crosses either line, plan the review into your timeline; see second story additions.
Timing rules after the permit
| Rule (Village Code § 24-10) | What it means |
|---|---|
| Start window | The permit authorizes starting work for three months after issuance |
| Continuous work | A lapse of more than 60 days is treated as abandonment unless extended |
| Extensions | Up to two, of up to three months each, for good cause |
| Permit card | Displayed on site, visible from the street |
The department’s entry form also flags whether a foundation survey, a final survey, engineered lumber or truss notice, or shoring and fencing are required for your job. A long gap between demolition and framing can cost you the permit, so line up the framing crew before the roof comes off.
Insurance
Contractors, plumbers and electricians working in the village need $1,000,000 combined single limit liability insurance naming the Incorporated Village of Rockville Centre as additional insured and certificate holder, plus workers’ compensation on the state’s forms. See how to check a contractor.
Rockville Centre’s houses
The Census puts Rockville Centre’s median year built at 1945, with 70.1% of homes built before 1960 (Census). Nassau County’s median is 1955 (Census), so the village’s housing runs older than the county’s; expect older framing and the asbestos affidavit on many projects. Nearby Oceanside and Baldwin file with the Town of Hempstead; Garden City has its own rules on Village of Garden City permits. The Building Department is at 110 Maple Avenue and can be reached at (516) 678-9247; confirm current forms there, since the posted package is several years old.
Frequently asked questions
When does a Rockville Centre project need Exterior Design Review?
The village's residential permit instructions list two triggers: a total project cost greater than $300,000, or an increase in total square footage of 1,000 square feet or more. If your second story costs more than $300,000 or adds 1,000 square feet or more, plan for the review.
How old can my survey be in Rockville Centre?
The instructions call for two copies of an accurate, legible survey to scale that's no older than five years.
How long do I have to start work after the permit is issued?
Under Village Code § 24-10, a permit authorizes starting work for three months after issuance, and work must continue actively. A lapse of more than 60 days counts as abandonment unless the Building Official extends it, with up to two extensions of three months each.
What insurance does my contractor need in Rockville Centre?
The village requires $1,000,000 combined single limit liability insurance naming the Incorporated Village of Rockville Centre as additional insured and certificate holder, plus workers' compensation on the state forms. Contractors also need a Nassau County home improvement license, and electricians and plumbers need Rockville Centre licenses.