The budget, line by line
| Line item | Figure | Source |
|---|---|---|
| Demolition, Long Island house | $11,400 – $24,100 | HomeBlue |
| Custom home, per sq ft (national) | $200 – $550 | HomeAdvisor |
| Custom home, national median per sq ft, 2025 starts, excluding lot | $171 | NAHB |
| Framing, labor and materials, multi-level house (national) | $10 – $19 per sq ft | Angi |
| Hempstead demolition permit, one- or two-family | $250 | Town of Hempstead posted schedule |
| Hempstead residential building permit | $200 + $18 per additional $1,000 | Town of Hempstead L.L. 20-2024 |
A worked 2,000 square foot example
| Item | Low | High |
|---|---|---|
| Demolition | $11,400 | $24,100 |
| Construction, 2,000 sq ft at $200–$550 | $400,000 | $1,100,000 |
| Subtotal before design, permits, utilities, septic | $411,400 | $1,124,100 |
Arithmetic on the published ranges above. We haven’t found a current, checkable Long Island per-square-foot figure for new custom homes, so the construction line uses HomeAdvisor’s national range. Under the Town of Hempstead’s 2024 residential formula, $200 plus $18 per additional $1,000, a $600,000 build’s permit would be $10,982.
Costs that don’t show up in per-foot prices
- Asbestos survey. New York’s Rule 56 requires a survey by a certified inspector before demolition; buildings whose construction began on or after January 1, 1974 are exempt from the survey but are assumed to contain asbestos when demolished unless documented otherwise (§ 56-5.1(b) and (c), ICR 56). Asbestos found is abated by a licensed contractor.
- Septic in Suffolk. Replacing a house triggers a county health department application, and nitrogen-reducing I/A systems have been required for new construction since 2021 (SCDHS presentation).
- Utilities. Disconnects before demolition and new electric, gas and water services after.
- Flood zones. A new house in a FEMA flood zone must be built to flood rules from the start, often elevated.
- Living elsewhere for the length of the build.
Rebuild or renovate?
Compare with second story addition cost and the full move-versus-build math in move or add on. For what happens on site, see teardown and rebuild and modular vs stick-built.
Frequently asked questions
Is it cheaper to renovate or tear down and rebuild?
Renovating is usually cheaper when the foundation and structure are sound and you're adding modestly. Rebuilding wins when the house needs most systems replaced, sits in a flood zone where a large renovation would force elevation anyway, or is much smaller than the lot allows. Price both with the same designer.
How much is the framing on a new Long Island house?
A small part of the total. Angi's 2026 figures put framing at $7 to $16 per square foot, or $10 to $19 for a multi-level house, so about $20,000 to $38,000 for a two-story 2,000 square feet, against a total build cost in the hundreds of thousands.
What costs do people forget on a teardown?
The asbestos survey and any abatement on pre-1974 houses, utility disconnects and new services, a new sanitary system on unsewered Suffolk lots, a current survey and soil work, and living elsewhere during construction.
What permit fees apply to a new house?
Each town has its own schedule. In the Town of Hempstead, residential building permits cost $200 plus $18 per additional $1,000 of estimated cost under Local Law 20-2024, and the town's older posted schedule lists $250 for demolishing a one- or two-family house.
Sources
- HomeBlue: cost to demolish a house in Long Island, NY
- HomeAdvisor: cost to build a house (custom homes per square foot, updated June 2026)
- NAHB Eye on Housing: custom home price per square foot, 2025 starts
- Angi: cost to frame a house (2026)
- NYS Department of Labor: asbestos survey requirements for building permit applicants
- Town of Hempstead: building department fees (posted 2018 print, demolition fee)
- Town of Hempstead Local Law 20-2024 amending § 86-11 fees (effective April 2, 2024)
- Suffolk County Department of Health Services presentation (posted by the Town of Shelter Island)
- NYS Department of Labor: Industrial Code Rule 56 (§ 56-5.1 survey requirement and exemptions)