Town of Huntington Building & Housing (Department of Engineering Services)
- Address
- Town Hall, Room 115, 100 Main Street, Huntington, NY 11743
- Phone
- (631) 351-2821
- Website
- huntingtonny.gov/building-housing
- Issues permits for
- Unincorporated hamlets such as Huntington, Huntington Station, Dix Hills, Melville, East Northport, Commack (part), Centerport, Greenlawn, Cold Spring Harbor and Elwood. Villages such as Northport, Huntington Bay, Lloyd Harbor and Asharoken issue their own permits.
How Huntington calculates the fee
Huntington doesn’t use your contract price. Code § 87-23 sets an “estimated construction cost” from the floor area of the work, then charges a $100 residential minimum plus $7 for each $1,000 of that estimate or fraction (Huntington 311).
| Type of residential work | Valuation per sq ft |
|---|---|
| One-story dwelling or one-story addition | $100 |
| Additional story | $80 |
| Dormer, unfinished basement, attached garage, heated enclosed porch | $50 |
| Change-of-use conversion, unheated enclosed porch | $35 |
| Finished basement, open deck, balcony, roofed-over deck | $20 |
Worked examples
| Project | Floor area | Valuation | Fee |
|---|---|---|---|
| Rear shed dormer | 400 sq ft | $20,000 | $240 |
| One-story rear addition | 300 sq ft | $30,000 | $310 |
| Second story over a ranch | 1,000 sq ft | $80,000 | $660 |
| Finished basement | 800 sq ft | $16,000 | $212 |
If construction or a change of use started before the permit, the fee is three times the normal amount. Try other sizes in the permit fee calculator.
Plans and survey
The town’s filing guidelines (Huntington filing guidelines) ask for:
- Three signed and sealed sets of architectural plans plus one copy, folded, no larger than 36 by 22 inches.
- A current survey showing all structures on the lot, dated within six months of filing.
- Site plans showing the proposed location; all structures must meet zoning setbacks.
For dormers, the town treats a single or double dormer wider than 50% of the roofline as a “full” dormer. Full dormers and second stories need the first-floor layout and cellar plan of the existing house, plus energy code compliance (Huntington 311).
Health department and demolition triggers
The filing guidelines note that residential additions may require Suffolk County Department of Health Services review, and new dwellings require it. Finished basements and converted garages need an egress window or a cellar entry direct to the outside and may also need county review. For demolitions, the town wants original utility disconnect letters and an asbestos letter for structures built before January 1, 1974. Read cesspools and additions before you add bedrooms.
Accessory dwelling units
Huntington issues a special, annually renewed permit for an accessory dwelling unit in an owner-occupied single-family house (Huntington ADU Bureau):
- The house must have had a certificate of occupancy for at least three years.
- Living space of the unit must be 300 to 650 square feet, not counting bathrooms and closets.
- A permit is needed whether the unit is for family, rent or the owner.
- No basement, cellar or attic apartment applications since July 16, 2019.
- On a sale, the buyer can take over the permit by filing within 90 days.
See mother-daughter additions and rooms over a garage for design options.
Filing
The Building and Housing division is in Town Hall, Room 115, 100 Main Street, Huntington, (631) 351-2821. Ask about villages: Northport, Huntington Bay and Lloyd Harbor run their own building departments.
Frequently asked questions
How much is a building permit for a dormer in Huntington?
Huntington values a dormer at $50 per square foot of floor area, then charges $100 plus $7 per $1,000 of that value. A 400 square foot dormer is valued at $20,000, so the fee is $100 plus $140, or $240. A 1,000 square foot second story is valued at $80,000, for a fee of $660.
What counts as a full dormer in Huntington?
A single or double dormer wider than 50% of the existing roofline. Full dormers and second-story additions need a first-floor layout and cellar plan of the existing house in addition to the new drawings.
How recent does my survey have to be?
The town's filing guidelines say the survey must show all structures on the lot and be dated within six months of the application.
Can I add an apartment for a parent in Huntington?
Through the Accessory Dwelling Unit Bureau. The house must be owner-occupied with a certificate of occupancy at least three years old, the unit's living space must be 300 to 650 square feet, and the permit is renewed every year. The bureau stopped accepting basement, cellar and attic apartment applications on July 16, 2019.