| Job | Published LI range | Median |
|---|---|---|
| Partial rear shed dormer (1 bedroom or office) | $35,000 – $55,000 | $45,000 (one builder's midpoint) |
| Full-width rear shed dormer | $40,000 – $100,000 | $80,000 |
| Dormer space without plumbing (bedrooms, office), per sq ft | $125 – $180 | $155 (one builder's midpoint) |
| Dormer space with a bathroom, per sq ft | $250 – $400 | $325 (one builder's midpoint) |
Ranges come from Long Island contractors' own published price guides. Method and every source: Long Island dormer and addition price survey.
Full vs half (partial) shed dormer
| Partial shed dormer | Full shed dormer | |
|---|---|---|
| Width | Part of the rear roof | Most or all of the rear roof |
| Typical result | One bedroom or office | Two or three bedrooms, often a bath |
| Published Long Island price | $35,000 – $55,000 | $40,000 – $100,000 |
| Town review | Standard dormer plans | Some towns ask for more. Huntington treats a dormer over 50% of the roofline as “full” |
The Town of Huntington puts a hard line on “full”: a single or double dormer wider than half the existing roofline. For those, the town asks for the first-floor and cellar layout along with the dormer plans (Huntington 311). Other towns define it differently or not at all, so your architect checks the local code.
How a shed dormer is framed
- Shore and open. The crew supports the ridge, then cuts the rear rafters and strips that section of roof.
- Floor first. If the engineer calls for it, they sister or add attic floor joists before any walls go up.
- Front wall. They build the new dormer wall on top of the existing exterior wall or set slightly back from it, with headers over each window.
- New roof. Shed rafters run from the top of the new wall up to the ridge or just below it. Hangers, ties or a structural ridge carry the load the old rafters used to carry as a triangle.
- Dry in. Sheathing, underlayment and roofing go on the same day or next, and the opening is tarped if not.
If your roof is built with factory trusses rather than rafters, the trusses can’t simply be cut; read trusses vs rafters first.
Angi puts an average dormer at about four to six weeks of construction, with larger shed dormers often running longer (Angi); the full path, permits included, is on how long a dormer takes.
Roof pitch is a code question
A shed dormer roof is much flatter than the main roof. New York’s 2025 Residential Code allows asphalt shingles down to a 2:12 slope and requires two layers of underlayment from 2:12 up to 4:12 (2025 RCNYS R905.2.2). Go lower and you need a low-slope system, such as a membrane or a suitable metal roof. The pitch also sets your headroom, so it’s worth settling with the architect early.
Wet or dry dormer space
One Long Island builder prices dormer space without plumbing at $125 – $180 per square foot and space with a bathroom at $250 – $400. The difference is the drain and vent routing through the first floor, the tile, and the reinforced floor under a tub. Place the upstairs bath over the kitchen or first-floor bath when you can, so the pipes have a short run down.
Next steps
See the full price picture on dormer cost on Long Island, how long it takes on dormer timelines, and what the inspector looks at on the framing inspection.
Frequently asked questions
Is a full shed dormer worth it compared to a partial one?
If you need two or more full-height bedrooms or a bathroom upstairs, usually yes. The roof is opened and the crew, dumpster and permit are paid for either way, so the extra width of a full dormer adds less than its share of floor area to the bill. A partial dormer makes sense when you only need one room or the town's rules limit the width.
How low can a shed dormer roof be?
Asphalt shingles are allowed down to a 2:12 slope under New York's 2025 Residential Code, and slopes from 2:12 up to 4:12 need two layers of underlayment. Below 2:12 you need a low-slope roof system, such as a membrane or a suitable metal roof, instead of shingles. Many Long Island shed dormers land in the 2:12 to 4:12 band, so ask what roofing your contractor plans to use.
Can a shed dormer go on the front of the house?
It can, but most Long Island homeowners put the big shed dormer at the back and keep the street side's original roofline, sometimes with small gable dormers in front. Some villages have architectural review boards that weigh in on front-facing changes, so check before you design one.
Does a shed dormer need new floor joists?
Often. The attic floor in many older Capes was framed as a ceiling, not a floor for bedrooms. Your engineer checks the joist size, spacing and span, then calls for sistering, added joists or a new floor system. That decision belongs in the stamped plans so every bidder prices it.