The framing inspection is a rough inspection. It comes after the walls, floors and roof are framed and sheathed, the roof and windows are in, and usually after the electrical, plumbing and HVAC rough-ins. It comes before insulation.
The checklist inspectors work from
| Item | What they look for | Code reference (2025 RCNYS) |
|---|---|---|
| Matches the plans | Beam and header sizes, joist size and spacing, posts where drawn | Approved plans |
| Sill anchorage | 1/2 in. anchor bolts no more than 6 ft apart, two per plate section, one within 12 in. of each end, nut and washer on each | RCNYS R403.1.6 |
| Wall bracing and headers | Braced wall panels where the plans show them; king and jack studs at headers | Plans, RCNYS chapter 6 |
| Joist notches and holes | Notches no deeper than 1/6 of depth and not in the middle third; holes no larger than 1/3 of depth, 2 in. from edges | RCNYS R502.8 |
| Stud notches and holes | Bearing wall studs: notches up to 25% of width, holes up to 40% (60% if doubled) | RCNYS R602.6 |
| Fire blocking | Blocking at floor and ceiling lines, soffits, around chimneys and pipe penetrations | RCNYS R302.11 |
| Connectors | Joist hangers fully nailed, roof uplift ties, hold-downs and straps where specified | Plans, RCNYS R802.11 |
| Bearing | Beams and girders bear on posts, walls or pockets with enough length | Plans |
| Stairs | Width, headroom, riser and tread size, guards | RCNYS R318.7, R321 |
| Egress | Bedroom windows with enough clear opening | RCNYS R319 |
Anchorage is in the foundation chapter (2025 RCNYS, chapter 4); drilling and notching rules are in the floor and wall chapters (2025 RCNYS, chapter 5; 2025 RCNYS, chapter 6). Fire blocking and egress are in chapter 3 (2025 RCNYS, chapter 3).
What commonly gets flagged on additions
- Plumbing cuts. A drain line notched through a joist near mid-span, or a stud wall bored too much for a stack.
- Missing fire blocking between the old and new framing, or around a new chimney chase.
- Hangers with missing nails, or the wrong hanger for the joist.
- Substitutions. A beam or header smaller than drawn, or a different product without an engineer’s approval.
- Bedroom windows too small for egress in a new dormer.
- Uplift connectors missing at some rafters, especially in high-wind areas.
How to pass the first time
Keep the approved plans and permit on site. Walk the job with your contractor before calling for inspection. Have the engineer review any changes before they’re built. Photos of the open framing are worth keeping for your records too. The inspection’s place in the job is shown on the addition timeline.
Frequently asked questions
Who calls for the framing inspection?
Usually the contractor who holds the permit, but check your contract. The building department needs the permit number and the approved plans on site. Some offices schedule online, others by phone.
What happens if the framing inspection fails?
The inspector lists what has to be fixed. The contractor corrects it and calls for a re-inspection. Insulation and drywall can't go in until it passes, so a failed inspection delays every trade after framing.
Can a plumber cut through a joist?
Only within limits. Under New York's 2025 Residential Code, notches in solid-lumber floor joists can't exceed one-sixth of the joist depth or sit in the middle third of the span, and bored holes can't exceed one-third of the depth or come within 2 inches of the top or bottom edge. Engineered joists follow the manufacturer's rules.
Is the framing inspection the same as the engineer's inspection?
No. The building inspector checks for code compliance. Some engineers also visit to confirm their structural design was built as drawn, and some offices ask for an engineer's letter. Ask your engineer whether a site visit is in their fee.
Sources
- ICC: 2025 Residential Code of New York State chapter 5, floors (R502.8 drilling and notching)
- ICC: 2025 Residential Code of New York State chapter 6, wall construction (R602.6 stud drilling and notching)
- ICC: 2025 Residential Code of New York State chapter 3 (R302.11 fireblocking, R319 emergency escape openings)