What legalizing costs in three towns
| Town | Normal residential fee | Work done without a permit | Extra paperwork |
|---|---|---|---|
| Town of Hempstead | $200 + $18 per additional $1,000 | $400 + $36 per additional $1,000 | Per the office |
| Town of North Hempstead | $250 initial; fee from its construction cost schedule | Two times the normal fee | Design professional’s certification letter and an electrical inspection certificate |
| Town of Huntington | $100 + $7 per $1,000 of floor-area valuation | Three times the fee | Per the office |
Sources: Hempstead L.L. 20-2024, North Hempstead requirements, Huntington § 87-23.
Worked example
A $100,000 dormer built without a permit in the Town of Hempstead: $400 plus 99 × $36 = $3,964, versus $1,982 if it had been permitted first.
The legalization process
- Get the records. Ask the building department for a property record search to see what’s on file. The Town of Hempstead charges $25 for one (Town of Hempstead).
- Hire a design professional to document the existing work and, where the town requires it, certify that it meets the building code. North Hempstead requires that letter for “maintain” applications.
- File to maintain the work, with a current survey and as-built plans.
- Open what the inspector needs to see. Framing, wiring and plumbing hidden behind drywall may have to be exposed. See what the framing inspection checks.
- Fix what doesn’t comply, then get the certificate of completion or occupancy.
Buying or selling a house with unpermitted work
Unpermitted dormers, finished basements and enclosed porches often surface at sale. Buyers’ attorneys compare the certificates of occupancy with the house. New York’s Property Condition Disclosure Act requires sellers to disclose known conditions, and as of March 20, 2024 sellers can no longer skip the form with a $500 credit (NYSBA). Options include legalizing before closing, a price adjustment or an escrow holdback; your attorney negotiates which.
Avoid it next time
Pull the permit before work starts, and make sure your contract says who files it. Our contractor check guide covers what to put in writing, and property taxes after an addition explains why permitted work also matters for the home improvement exemption.
Frequently asked questions
What happens if I build an addition without a permit on Long Island?
The town can issue violations or a stop-work order, and the work can't get a certificate of occupancy or completion. Legalizing it later costs more in fees and may require opening walls. Unpermitted work also complicates insurance claims, refinancing and selling.
Can I sell a house with an unpermitted dormer?
You can, but buyers' attorneys and lenders typically check the certificate of occupancy against the house. Unpermitted space can delay closing, reduce the price or require legalization first. New York's property condition disclosure statement also asks sellers about known conditions.
How do I legalize unpermitted work?
Typically: hire a design professional to document and certify the existing work, file a permit application to maintain it, pay the higher fee, and pass inspections, which may mean opening finishes so the inspector can see framing, wiring and plumbing. Get a current survey too.
How do I check whether a house has open permits?
Ask the building department for a property record search. The Town of Hempstead, for example, offers a Building Department record search for a $25 fee. Compare the certificates of occupancy on file with what's actually built.
Sources
- Town of Hempstead Local Law 20-2024 amending § 86-11 fees (effective April 2, 2024)
- Town of North Hempstead: requirements for submittal of a residential building permit (maintain permits)
- Town of Huntington 311: building permit application fees (§ 87-23F, unauthorized construction)
- Town of Hempstead: mother-daughter use (Building Department record search fee)
- New York State Bar Association: Property Condition Disclosure Act amended